Surfacing
Weekly Update #33
9
December 2004
SURFACING IS COMPLETED ON ALL MAJOR
PROJECTS!!!
As of December 9th
we have surfaced well over the 800 pass miles that we had scheduled to be
surfaced this year. Some of the
surfacing crews will continue to surface as long as possible to further improve
rough areas on the properties.
The 255,000 tons of ballast
is nearly three times what has been normally used on these two properties.
Crews continue to spot
surface on the Black Hills and PRC subs of the DM&E and on the
As is the case with the
other major programs, management and employees are working on estimates to
project which surfacing projects and how much ballast will be needed for the
2005 season.