Ties
Weekly Update #1
16
April 2004
ON SCHEDULE
To
date, we have installed 9,000 or the 182,000 ties scheduled to be installed by
November 24th 2004. As of
now, it appears we will meet that schedule.
We have made some modifications to the plan by focusing more resources
on the IC&E “exempted” track south of Owatonna, thus taking away some of
the early effort on the DM&E. But
basically, we are on track with the overall program.
¨
DME
Tie gangs were scheduled to start on April 5. They trained and went over safety
requirements the first few days and began installing on the 8th.
¨
The
LA Colo gang on the IC&E started on the 5th with a partial
crew. The LA Colo gang that was
scheduled to start on DM&E on April 12 did not start due to a change in
plans. Both crews will now be working
on the IC&E and will finish that project on time.
¨
As
of April 15, 2004 120,000 ties have been delivered.
¨ The remaining 62,000 ties are scheduled to be here by June 30, 2004
¨ As of April 15, 2004 a total of 9,000 ties have been installed.