Ties
Weekly Update #4
6
May , 2004
AHEAD OF SCHEDULE
As
of 6 May, we have installed over 43,000 of the 182,000 ties scheduled to be
installed by November 24th 2004.
As of now, it appears we will meet or beat that schedule. We modified the plan by focusing more
resources on the IC&E “excepted” track south of Owatonna, thus taking away
some of the early effort on the DM&E. The crews completed the Owatonna sub
ties on Saturday the 2nd and started the DM&E Waseca sub ties on
Tuesday the 4th. We still expect all of the tie installation east of
Mankato on the Tracy and Waseca subs to be completed by the end of May. At that
time the LA Colo crew will relocate to Sleepy Eye and start tie installation at
that location. Production levels on all crews have been above expectations
because of high equipment reliability and excellent track time and we expect
the tie installation to remain ahead of schedule through out the remainder of
the season.
¨
All
crews are on or ahead of schedule
¨
As
of 6 May, 135,000 ties have been delivered.
¨
The
remaining 47,000 ties are scheduled to be here by July 30, 2004, although there
is still concerns over the availability of gons for delivery
¨
DME
tie gang in the Lake Preston (Wes Risseuw, foreman) area has completed
approximately over 5.0 miles of ties and ballasting. Surfacing will begin soon behind this crew to remove a 10 MPH
slow order. This was not scheduled to
be done until August, but was moved ahead in the schedule to improve train
speeds in the area for the transportation department.
¨
The
LA Colo tie gang completed the tie
installation on the Owatonna sub on Saturday the 1st of May. They
then started installing approximately 20,000 ties east of Mankato on the
DM&E before starting at Sleepy Eye with the Supplemental tie program.
¨
After
LA Colo tie crew completes the tie installation on the Owatonna sub, we will do
some spot surfacing and expect to remove this track from the FRA “excepted”
status by May 14th.
¨
The
DME West tie gang (Jim Nemec, foreman) continues to improve on their production
numbers and will be installing ties just south of Rapid City for the next
several weeks
¨
The
IC&E tie crew, under new tie gang foreman Steve Koser, started at Plymouth
and are now just south of Austin. We expect this crew to complete the Owatonna
sub around the end of May.