Ties
Weekly Update #7
27
May, 2004
AHEAD OF SCHEDULE
As
of 27 May, we have installed over 65,000 of the 182,000 ties scheduled to be
installed by November 24th 2004.
All crews, both contractor and company are doing an excellent job and
are ahead of schedule.
¨
As
of 27 May, 155,000 ties have been delivered.
Because of the shortage of gondolas we now expect the delivery of ties
to be completed by the end of July or middle of August
¨
DME
tie gang in the Lake Preston (Wes Risseeuw, foreman) will finish up the Lake
Preston/ De Smet section of track next week and with the help of Earl
Ruchdaschael’s surfacing crew, we will start removing slow orders from this
area within the next couple weeks. Tie crew has completed over 10 miles of tie
installation progress.
¨
This
crew will now make the first pass tie installation from Volga to Lake Preston
and then will help with the siding construction.
¨
The
LA Colo tie gang has started at MP 180 and will continue toward Garvin with an
expected completion date of June 25th.
¨
All
ties are installed on the Owatonna sub and Foreman Steve Koser’s crew is now
installing ties in the Calmar area and then will install another 5,000 ties
west of Mason City prior to installing curve rail east of Mason City.
¨
The
DME West tie gang (Jim Nemec, foreman) continues to improve on their production
numbers and will be installing ties just south of Rapid City for the next
several weeks.