Ties
Weekly Update #9
10 June, 2004
CONTINUING GREAT PRODUCTION
As
of the 10th of June, we have installed over 90,000 of the 182,000
ties scheduled to be installed by November 24th 2004. All crews, both contractor and company are
doing an excellent job and are ahead of schedule.
¨
As
of the 10th of June, 160,000 ties have been delivered. Because of the shortage of gondolas we now
expect the delivery of ties to be completed by the end of July.
¨
Wes
Risseeuw’s DM&E east tie gang has completed tie installation between Lake
Preston and De Smet and after ballasting and surfacing; this section of track
will be raised to 30 MPH. We expect
this to be complete by the end of June. This crew will now make the first pass
tie installation from Volga to Lake Preston and then will help with siding
construction projects.
¨
The
LA Colo tie gang has started at MP 180 and will continue toward Garvin with an
expected completion date of June 25th. They are currently at MP 200
near Sanborn.
¨
Foreman
Steve Koser’s crew is now installing ties in the Calmar area. He expects to complete early the week of
the 14th and then will install another 6,000 ties west of Mason City
prior to installing curve rail east of Mason City. We expect the tie installation to be completed by mid July.
¨
Jim
Nemec’s west tie gang continues to improve on their production numbers and will
be installing ties just south of Rapid City for the next several weeks. Average
weekly production for this crew of new hires is nearly 1000 per week.