Ties
Weekly Update #15
22 July, 2004
CONTINUING EXCELLENT PRODUCTION
As
of July 22nd, we have installed over 135,000 of the 206,000 ties now
scheduled to be installed by November 24th 2004. All crews are doing an excellent job and
should complete all projects on or ahead of schedule.
¨
As
of July 22nd, over 195,000 ties have been delivered to our
properties. We now expect the delivery
of ties to be completed by the end of July or early in August.
¨ Wes Risseeuw’s DM&E east
tie gang has taken a short break form their tie installation duties to help
with the construction of the Elkton and De Smet sidings. Once those sidings are
completed Wes will return to his tie installation duties from De Smet toward
Huron.
¨
The
LA Colo tie gang has completed their first three sections of tie installation
on the IC&E and DM&E and will now focus on the CWR project on the
IC&E. This crew has already
installed ties between Austin and Owatonna on the IC&E, and between
Owatonna and Mankato, and Sleepy Eye and Garvin on the DM&E. They still need to complete the tie installation
between Garvin and the Minnesota South Dakota state line later in the year.
¨
Foreman
Steve Koser’s crew has completed the installation of 6,000 ties west of Mason
City and will be traveling eastward to begin installing switches in the Calmar
rail project area, then installing CWR on the IC&E’s curve patch
program. They will spend most of the
remainder of the year on this curve patch project, except for a short period of
time when they will install about 5,000 ties in the Quad Cities area in September
¨
Jim
Nemec’s west tie gang has completed the section of tie between Rapid City and
Hermosa. After one week of installing
rail south of Fairburn, they will travel to Dakota Jct. to install more ties at
that location.
¨
The
RJ Corman tie crew began installing ties on Friday the 16th at Volga
and will install ties from Volga to Lake Preston, then turn the crew and
install from Volga to the state line. They are expected to have this completed
by early September.