Ties
Weekly Update #26
14
October, 2004
CONTINUED EXCELLENT PRODUCTION ON ALL CREWS
As
of October 14, 2004, we have installed over 220,000 of the 245,000 ties now
scheduled to be installed by November 24th 2004. The tie crews had an excellent week of
production!!
¨ Due to favorability in some
of our other projects we have been able to commit to another 10,000 ties in the
Quad Cities area and these ties will be installed by the end of this week by
Mr. Koser’s crew.
¨ As of October 14, over 240,000
ties have been delivered to our properties and are either installed, on the
ground, or in the process of being unloaded by the Brandt truck.
¨ Taking all things into
consideration, the siding additions, the siding extensions, the
¨ The Railworks tie crew will
finish into Huron today, the 14th and will load out their equipment
over the weekend.
¨ The LA Colo tie gang will
complete their portion of the project up to the east switch at Elkton on Friday.
This crew will then move to
¨ Jim Nemec’s west tie gang
has completed the tie installation in the Smithwick area. For the remainder of the year, this crew will
be installing ties between Wasta and Wall and will assist with a switch project
at Colony.
¨ Wes Risseuw’s tie crew, who
has been busy on siding projects for the past several months, will return to
tie installation on the 25th of October on the PRC subdivision on
the DM&E west of