Ties
Weekly Update #27
21
October, 2004
TIE PROJECTS WINDING DOWN!!!!
As
of October 21, 2004, we have installed nearly 230,000 of the 245,000 ties now
scheduled to be installed by November 24th 2004. The two contract tie crews on the DM&E
and the IC&E crew completed projects this past week!!
¨ Steve Koser’s crew finished
their tie installation projects for the year with the completion of a 10,000
tie project near
¨ The LA Colo crew completed
their portion of DM&E’s tie project this past week with their completion of
installing nearly 25,000 ties on the east end of the Huron sub. This crew will now install about 10,000 ties
on the IC&E near
¨ The Railworks tie crew
completed their portion of this year’s project installing nearly 20,000 ties on
the west end of the Huron sub. Part of
this crew will travel to
¨ As of October 21 over
240,000 ties have been delivered to our properties and are either installed, on
the ground, or in the process of being unloaded by the Brandt truck and others.
¨ Taking all things into
consideration, the siding additions, the siding extensions, the
¨ Jim Nemec’s west tie gang
has completed the tie installation in the Smithwick area. For the remainder of the year this crew will
be installing ties between Wasta and Wall and will assist with a switch project
at Colony.
¨ Wes Risseeuw’s tie crew, who
has been busy on siding projects for the past several months, will return to
tie installation on the 25th of October on the PRC subdivision on
the DM&E west of