Ties
Weekly Update #30
11
November, 2004
LAST TWO TIE PROJECTS NEARING COMPLETION!!
As of November 11th, 2004, we have
installed over 240,000 of the 245,000 ties now scheduled to be installed by
November 24th 2004. The last
two tie projects for 2004 were started last week with Wes Risseeuw’s crew
installing ties on the PRC sub of the DM&E and the LA Colo crew installing
ties on the
Preparations are now being made for the 2005 and
beyond tie programs as well as all of the other capital programs on both
properties. Preliminary figures indicate
we should be installing somewhere in the vicinity of 125,000 ties for the 2005
year.
¨ Steve Koser’s crew finished
their tie installation projects for the year with the completion of a 10,000
tie project near
¨ The LA Colo crew began
installing over 10,000 ties on the double track of the
¨ Jim Nemec’s west tie gang
will be installing the last 2,000 ties of their production year over the next
couple weeks near
¨ Wes Risseeuw’s tie crew will
complete the installation of nearly 7,000 ties near
¨ Taking all things into
consideration, the siding additions, the siding extensions, the